Wednesday, October 23, 2013

Latest House Construction Cost, Rates and Estimated Time of Completion in Lahore - Pakistan (Updated on November 17, 2015)

(Special thanks to Nadeem Aftab Sahib who provided updated rates. His comments on the end of this post would help to understand the matter further.)

Labour Rate (Without material) Construction Cost (Updated on November 17, 2015)

Rates of Covered Area Rs.240/= to Rs.260/= per square ft.
Basement Rs.320/= to Rs.360/= per square ft.





Masonry work: Rs.25/= per square ft.
Plaster work: Rs.15/= per square ft.
Marble work: Rs.20/= per square ft.
PCC floor before tile / marble: Rs.20/= per square ft.
Excavation with machine (Free if you do not need excavated soil): Rs.2/= per Cft

MATERIAL Rates  
Bricks: Rs.7,500/= for 1000 (Pattoki)
Sand Chanab: Rs.25/= Cft
Sand Ravi: Rs.10/= Cft (Ask for Mehmood Booti area)
Crush Sargodha: Rs.55/= Cft (if you buy directly from crusher)
Steel: Rs.88,000/= per Ton (it includes carriage, loading, unloading of 2000 tons)


Grey Structure Construction Cost (including material)

Rs.1200-1300 per square ft.




Finished (Turnkey) House Construction Cost

  1. Rs.2,000/= per square ft. (Normally Good)
  2. Rs.2,500/= per square ft. (Excellent)
  3. Rs.2,700/= per square ft. (Luxury)
These rates does not include water tank, septic tank, porch area, main gate, and boundary walls etc.
Moreover Pergola (front elevations) rate are taken as 50% of covered area rate.


Estimated Time of Completion

Generally the contractor would be ready to make a contract to complete a home (up to six months) but practically completion is not possible before 8 months. Labour class goes to their native area and work is fully stopped for at least two weeks on each Eid, Moharram and in April (to take part in wheat crop cutting). In general, labour belongs to same family / area so in some Khushi Ghammi they leave the work and come back only when nothing is left in their pocket.
After understand all these factors I would suggest that one should keep at least 8 months in the mind for completion of a home but the contract should be made of 6 months. If mutually agreed then some plenty should be included in the contract clause in case the responsibility of late lies on contractor and vice versa. There is no harm for decided an appreciation clause if the project is completed before time. This may be Rs.500 per day if the work is late by 15 days and Rs.1,000/= for more period of time.

I understand that this plenty would be only to pressurize the contractor and a moral obligation. It may help in avoiding unnecessary delay in the work.


December 2015 ------- I have been receiving requests from my readers of this blog to recommend a reliable contractor to them. I am sorry that I can not take responsibility of any one. 
Few friends gave good feedback about Muhammad Yousaf working in Bahria Town Lahore and surrounding area. If interested, you may contact him on your own responsibility.

Mr Yousuf 03009509487 & 03014173754 

======= Please visit following posts for further information =======

86 comments:

  1. Hello Hussain Kaisrani,

    I read your article. It is very informative and to the point. It's been nice knowing you. I wish you have a bright future and all the best for your MA degree.

    ReplyDelete
    Replies
    1. Thanks for your comment and wishes for my MA degrees.

      Delete
    2. Mr Hussian,

      Can you please share Bahria Bylaws book? I am out of country and wanted to go through this as I am interested to construct a house in bahria lahore.

      uetian04@gmail.com

      Thanks,

      Naveed

      Delete
    3. Anonymous9:18 pm

      Dear Mr Hussain

      I have forwarded mail on your person ID Kaisrani@gmail.com, kindly manage to reply at your convenience. my mailing ID is aleyousfi@hotmail.com.
      regards

      Delete
    4. AOA, Sir I want to construct 1 kanal house (Single story) 3 bed rooms.
      In this regard I met with different builders and contractors but not satisfied by their behavior n work so I have some ambiguities in my mind so kind help me. My email address is hasnain-ak@hotmail.com

      Delete
  2. Dear Hussain. Thank you for such a wonderful insight into the dark and murky world of house construction in Pakistan. It is most enlightening. As you must have learnt you will encounter more questions then contributing comments. Hence my preamble. I would be extremely interested in finding out if the rates you mentioned are the same or there has been an increase.
    Regards. Dr. Shahid

    ReplyDelete
    Replies
    1. Dr. K. Shahid Sahib,
      Salaam,
      Sorry for late response as I am not in Pakistan and traveling.
      The rates are almost same. Depending upon the quality of work and workmanship one can go little bit higher. Thanks.

      Delete
    2. Salaam dear Mr Hussain kaisrani,
      I want to built a 4 marla commercial building,can you send me your number or office address?

      Delete
    3. Salaam dear Mr Hussain kaisrani,
      I want to built a 4 marla commercial building,can you send me your number or office address?

      Delete
  3. Hussain bhai, very enlightening to read someone helping community by means of advice. JazakAllah... I shall soon return to read more as I am planning to build my first small house, inshAllah!

    ReplyDelete
  4. Dear Hassain Sb, Excellent information. Can you please update as you described in your further links.

    ReplyDelete
  5. what is rate of plaster per square feet area tc

    ReplyDelete
    Replies
    1. It is not a routine work so I am not in the position to inform your about plaster rate. It also depends on which area of the building do you want to get plaster work done. Moreover how much work is required.

      Delete
  6. Anonymous10:54 pm

    Ho Bro. Thanks for very informative sessons.What u think about the pricing offered by the builders inside bahria town. are tehy too expensive or it make sense to buy home from them

    ReplyDelete
    Replies
    1. Generally they are very expensive. Secondly you may not get a house which fulfills your requirement. Quality is another issue about which we are not sure whether builder has maintained it or not.

      Delete
  7. Salam
    Thanks for the useful information. It will be much more helpful if you kindly let us know about the estimated time of completion
    Thanks

    ReplyDelete
    Replies
    1. Thank you very much for your suggestion dear Zarak Khan Sahib. I will be including the suggested information in the main post area.
      Regards.

      Delete
    2. Estimated Time of Completion
      Generally the contractor would be ready to make a contract to complete a home (up to six months) but practically completion is not possible before 8 months. Labour class goes to their native area and work is fully stopped for at least two weeks on each Eid, Moharram and in April (to take part in wheat crop cutting). In general, labour belongs to same family / area so in some Khushi Ghammi they leave the work and come back only when nothing is left in their pocket.
      After understand all these factors I would suggest that one should keep at least 8 months in the mind for completion of a home but the contract should be made of 6 months. If mutually agreed then some plenty should be included in the contract clause in case the responsibility of late lies on contractor and vice versa. There is no harm for decided an appreciation clause if the project is completed before time. This may be Rs.500 per day if the work is late by 15 days and Rs.1,000/= for more period of time.
      I understand that this plenty would be only to pressurize the contractor and a moral obligation. It may help in avoiding unnecessary delay in the work.

      Delete
  8. Anonymous8:19 am

    Thank You Mr. Kaisrani for your nice advice..

    would You plz guide us whether electrical, sanitary and tile work included in the grey structure or we have to pay extra cost for that??

    ReplyDelete
    Replies
    1. Thanks for your comment.
      Grey Structure (for general understanding) includes only whatever looks grey only. Electrical, sanitary and tile work is NOT included in it. All these works start after the completion of grey structure. Yes! we need to pay extra cost for these works.
      Thanks.

      Delete
  9. Shoaib9:54 pm

    Just found this article in one of google search results
    very helpful
    and..
    there should one on safeguarding oneself from fraudulent trickries of contractors and material suppliers

    ReplyDelete
  10. Anonymous12:49 am

    Sir, would u plz let us know what should be the minimum size of the porch or garage so that a normal car with dicky can be parked there??

    ReplyDelete
  11. Anonymous3:50 am

    whats ur contact no! Please text me with name i will call u back !! 0334 8666606! Waiting!!

    ReplyDelete
  12. Anonymous1:26 pm

    Thanks Hussain for such a nice details. Can you please help me with calculating cost for single roof area 30x30. from DPC till plastering only. No finishing. Also please consider rates for Islamabad in Bani Gala area. I need both with material and with out material rates.

    I will be grate full.

    Best regards,

    Aamir

    ReplyDelete
    Replies
    1. Dear Amir
      We supply all construction related material like tiles ans sanitary fitings For any kind of information please contact us prove u the samples and the picture on whats app
      03005555821
      03455600061
      imran Aslam

      Delete
  13. Hussain Kaisrani Although you are not engineer but still its Really Nice to see such interesting information
    Have a look at my albums.These will also help you in knowlege

    www.facebook.com/home2015

    ReplyDelete
  14. usman8:43 am

    Dear Mr. Hussain,

    Can you pls. tell how much steel in tons, cement bags, bricks, sand and crush is used in average for 1 kanal house ??

    ReplyDelete
  15. Can you pls. tell how much steel in tons, cement bags, bricks, sand and crush is used in average for 1080 fits house ??

    ReplyDelete
  16. Anonymous7:54 am

    Good compilation!
    Are Rates same in Karachi?
    Where can I find last 50 years historical rates?
    Thx

    ReplyDelete
  17. Great work you have done. Is it further possible to prepare a calculator for cost of constructions as per squ ft area

    ReplyDelete
  18. Anonymous7:51 pm

    no doubt it is a great job. can you guide me that what should be the depth of the base ( Buniyad ) ?

    ReplyDelete
  19. Dear Hussain Kaisrani, its very informative, can u plz mention the average cost and time of construction of ground + 4 on 100 yards commercial plot in dha karachi. your reply will be appreciated

    ReplyDelete
  20. Anonymous1:39 pm

    what is the cost of boundry wall per Square ft?

    ReplyDelete
  21. Anonymous4:46 pm

    Dear Hussain
    i have one kanal plot in Behria town sector c.lahore.
    i paid all instalments about 5 years ago but didnot take the possesion yet.
    on that time they told me if i dont want to take possesion then i have to pay 500 rupees
    per month.i am not sure if i am going to build a house or sell it.
    is there any problem if i leave my plot like that. becasue i am not ready yet.
    i will be very thankful if you answer me.
    imtiaz

    ReplyDelete
    Replies
    1. No problem at all. You may leave your plot like that.

      Delete
  22. Thank you Mr. Hussain for providing this price list. This will give a rough estimate on how much we need to spend in our house. By the way, can you please visit this site: Topnotch Construction PH.

    ReplyDelete
  23. Naveed6:51 am

    Can you please guide us on getting House on Rent without involving Property Dealers

    ReplyDelete
    Replies
    1. I am not in favour of getting a house on rent without involving Property dealers. Sorry.

      Delete
  24. Anonymous11:05 am

    Dear Hussain Kaisrani Sahib
    Thanks a lot for sharing excellent information.Indeed a great job.
    Can you please tell us the commercial construction cost and time frame in DHA Lahore for a 8 Marla plaza having an area of 9000 Sq Ft.
    Best Regards

    ReplyDelete
    Replies
    1. Salaam, Sorry that my information in commercial construction is very limited. Thanks.

      Delete
  25. fahad hoti10:31 am

    would u please share facebook page. My question is that does the turnkey labor rate include wooden false ceiling and wardrobes and angeethees and doors etc

    ReplyDelete
    Replies
    1. fahad hoti Sahib,
      I don't think that you need my facebook page to get information about your queries.
      Secondly you don't need to ask for facebook page. Only put the name or email address in facebook search and you will reach there.
      Yes! in turnkey everything you mentioned is included but both the parties should mutually agree upon it by signing the contract. Thanks.

      Delete
  26. javaid kausar dar12:54 am

    Dear Hussain,
    Its really encouraging to find out that we still have person like you who are willing to work with honesty and dedication in our country well known for cheaters in every walk of life. People have lost confidence and are scary to make any commitments when it comes to project like construction of a house which is going to consume ones life time saving( if Hallal).
    I got one Kanal plot in bahria town Lahore and looking for an honest person to construct my 5 bed room villa, if you can offer yourself , please do contact me.
    regards
    javaid

    ReplyDelete
    Replies
    1. Anonymous1:19 am

      Wajid Associates

      Architects
      Interior Designers
      Contractors
      Landscape consultants

      Feel free to contact 03028440337

      Delete
  27. Dear Javaid Dar Sahib,
    Thanks a lot for your kind remarks brother.
    Due to my official commitments I am not in the position to assist you. Sorry.
    I wish you all the best in construction of your Villa.
    Best regards,
    Hussain Kaisrani

    ReplyDelete
  28. Dear Hussain
    With best wishes,Your In formations are highly appreciable and best for public.
    I am evaluating the cost of a home construction on 240 yards(Total area 2160 sq ft) but allowed covered area is 1800 or 1600 sq ft which is not confirmed by me) second question how to control the budget or cost control from accessories or fittings,paint,tiles or floor type, stairs and else.Please reply me.
    Syed Ahsan

    ReplyDelete
  29. Dear Mr Kaisrani, I have few questions, if you can kindly reply
    1, Is the rate of construction same for ground and 1st floor
    2, what are the rates of architects and others before starting construction
    3, what is the procedure in DHA and Bahria before i can start construction and how much it costs
    4 Are you in favour of making a basement in 5 marla residential, what are the advantages and dis advantages
    5, I am living abroad, if i make a contract for grey structure construction with someone, is there any way i can check the materiel and quality of work, do i need to hire someone for this ? if yes to whom ?
    6, do i need to pay full amount in advance or in stages

    ReplyDelete
  30. Dear Mr Kaisrani, I have few questions, if you can kindly reply
    1, Is the rate of construction same for ground and 1st floor
    2, what are the rates of architects and others before starting construction
    3, what is the procedure in DHA and Bahria before i can start construction and how much it costs
    4 Are you in favour of making a basement in 5 marla residential, what are the advantages and dis advantages
    5, I am living abroad, if i make a contract for grey structure construction with someone, is there any way i can check the materiel and quality of work, do i need to hire someone for this ? if yes to whom ?
    6, do i need to pay full amount in advance or in stages

    ReplyDelete
    Replies
    1. Salaam dear Irfan uae,
      Please see into my reply point by point.
      1. No, the rate of construction on ground floor is significantly high if you make a contract for only one floor. In case of complete house construction, the contract is made on the basis of covered area which is same for all house.
      2. It depends upon your plot size, selection of architect and housing project.
      3. I am not aware of DHA procedure. For Bahria Town you need to apply for construction of your house in Bahria Design Wing by providing copy of ID card, possession and allotment letter. They will issue you a challan form payable in NIB bank. You will get a map designed and approved and then can start construction of your house. The process takes around one month if you have done your home work properly.
      4. For a 5 Marla plot it is generally not feasible. The cost increases a lot which an owner of 5 Marla plot can not afford.
      5. Practically speaking that you can not check. Whether you are in Pakistan or abroad you need to hire some one who will be responsible to receive and count and take care of the material at site. An experienced Chowkidar can do it very well.
      6. In stages.
      Good Luck!

      Delete
    2. Irfan bashir sb if you want contact with us al hussain construction company 03469692858

      Delete
  31. Thanks a lot Mr Kaisrani

    ReplyDelete
  32. Hussain Sahib! Thank u very much for always providing us good information related to world of real estate and construction.

    Since I have been in this field too. I have some butterflies in mind related to the cost of construction.

    As far as grey structure is concerned, you calculation is fine but for finishing i might have different outlook viz

    If i take a home with covered area of 4000sqft in Bahria town then it will trickle down like this 1200*4000=4800000
    Wood work, the labour of wood work in islamabad is hovering around 250000/- and ash wood is being rated @2600 and it will roughly will not less than 1M since buying sheets, locks, and related tools make it too expensive. Only the material will cost around not less than 7 lac rupees if u go for engineered doors. frames made of ash wood and inside sheet of ZAK etc.

    If u go for normal china or master tiling and in set backs and porch marble with top flooring, u will never end up having cost less than 1 M.

    Good quality glass and aluminium say 1.6mm will cost around 500 per sqt.It will also cost u around 300000. Main gate will cost not less than 60K, The electricity fittings will cost around 300000/- Each wash room will cost sonex normal fittings around 30000/- totalling not less than 200000/- in any case. Door and cuboard polishing will have cost not less than 100000/. The colour if used ici/berger/kansai will only have labour rate around 150000-175000/- and material will cost not less than 250000/- making it total more than 500000/- with good 3 coats including weathershiled.

    So bhai jaan if u look it rationally, it will not less than 2500 persqt for good finish. and for very ordinary finishing cost will be around 2000/-. In our construction work, it is well established that how much is spent on grey structure will fetch atleast the same amount for finishing. A number of things which i am not mentioning here will crop up when u ll go for actually finish home like jalis, safety grills, stair marble, kitchen marbles and many more.

    ReplyDelete
    Replies
    1. your made point there, since i am doing construction business you need very reliable constructor who just not hide things because you are not paying well and costs are high.

      Delete
  33. Hussain sahib thanks for input. But frankly speaking since i m in this field and i know really well that after all of efforts the finishing cost is equal to the grey structure cost and that's y in market good finishing cost is not being quoted less than 2300 psq. with low quality avg finishing will cost around 2000 psqf.

    tc

    ReplyDelete
    Replies
    1. Dear Nadeem Aftab Sahib,
      Bhai Jaan! Thank you so very much for taking all the trouble in providing all the detail. I am not involved in construction anymore so my information and experience is VERY limited.
      I will see into your details again and will make appropriate changes.
      Highly Obliged for your guidance.

      Delete
  34. Anonymous6:10 am

    Dear Kaisrani sb

    i have a porch of chips and sheesha(old style) of approx. 1000 soft. What would it cost me to:
    Break and dispose the old chips and concrete
    then put ''rorree'' if necessary ,then put concrete 4 inch
    Then put tiles on this.
    what kind of tiles should be put on porch and what is the medium quality tile costs/

    Thanks
    Shakeel

    ReplyDelete
  35. nadeem ali8:20 pm

    nadeem aftab can u provide ur cell no i am planning to construct a 5 marla house in dha phase 5/6 i need ur technical advice and help u can me at 03225638964 thanks for the immense knowledge u shared here it is a great help

    ReplyDelete
  36. hello Hussain can please update me the latest rates for grey construction your blog is
    one yes please update for current situation as on NOV -2015

    ReplyDelete
    Replies
    1. Dear Azhar Farid!
      The post is now updated. Please also go through the comments of Nadeem Aftab Sahib.
      Thanks.

      Delete
  37. Hussain sb mein ne 5 marla ka upper portion construction kerwana hai grey structure per kitna kharcha a jaye ga. Location punjab govt employee society near bahria. Covered area sq foot i think 1000 ho ga

    ReplyDelete
  38. Sir kindly tell me this labour cost is for double stroy construction or for single stroy ..im going to construct 15 house so thatswhy I want to clear this thing...

    ReplyDelete
    Replies
    1. The labour rates are for a standard double storey house. Thanks.
      Good Luck!

      Delete
  39. Sir kindly tell me this labour cost is for double stroy construction or for single stroy ..im going to construct 15 house so thatswhy I want to clear this thing...

    ReplyDelete
  40. Sir kindly tell me this labour cost is for double stroy construction or for single stroy ..im going to construct 15 house so thatswhy I want to clear this thing...

    ReplyDelete
    Replies
    1. Sar Men construction thekedar hon Construction ke kaam ke liye rabta karen hamary han With matireal Lebar reet Satechar Finishing ka kaam kiya jata hai
      03002363125

      Delete
    2. Sar Men construction thekedar hon Construction ke kaam ke liye rabta karen hamary han With matireal Lebar reet Satechar Finishing ka kaam kiya jata hai
      03002363125

      Delete
  41. Dear Hussain SAhib! Thank u very Much for deep insight u are sharing for new entrants. I remained busy and couldn't follow further. However, I will be very much pleased if i can have a help in construction matters esp for those who are new. Should have any query related to construction may be asked. Kaisrani sahib thanks a lot once again for helping people in understanding the wizard of construction via your useful blog.

    Humble regards

    Nadeem aftab

    ReplyDelete
  42. Dear Sir further to your rates i might suggest a bit adaptations

    Plaster work good rate is rs:10-12 on running foot basis. for understanding sake;A wall of 11ft height and 20feet wide will be 220running feet.

    here in islamabad now tasi karandi rate now in the range of rs:250-350 depending upon the contractor work performance. an expensive contractor is one who makes u free from all headaches and is self motivated
    colour exterior / interior rate is 10-12 running ft

    i ll post more info soon

    ReplyDelete
  43. Anonymous9:47 am

    If you need details about construction cost in Lahore for current year 2015, you can visit this blog http://rhoninblog.blogspot.com/2015/12/house-construction-in-lahore-pakistan.html

    ReplyDelete
  44. Here is another helpful article for latest construction rates in Lahore for 2015 and it has lots of other details as well http://rhoninblog.blogspot.com/2015/12/house-construction-in-lahore-pakistan_28.html

    ReplyDelete
    Replies
    1. Thank you dear Asad for sharing a wonderful link. I was amazed to read the article of Mr Tauseef Afzal. He has provided latest information about material rates and shared his first construction experience in detail.

      PART 1
      http://rhoninblog.blogspot.com/2015/12/house-construction-in-lahore-pakistan.html

      PART 2
      http://rhoninblog.blogspot.com/2015/12/house-construction-in-lahore-pakistan_28.html

      Delete
    2. Hello Hussain sb, First of all thanks for mentioning the links in your comments, it was truly an inspiration from you that I wrote articles based on my own construction experience, just to help other fellow Pakistanis who wants to construct their houses and have no prior experience or knowledge of construction (Like Myself).

      Regards

      Delete
  45. dear husnain sb good informathion you house thanks

    ReplyDelete
  46. Muhammad hasseeb hussain
    From
    Sufi construction services
    03028787166
    03214567017
    Ha77eebhu77ain@gmail.com
    https://m.facebook.com/Sufi.constrction/

    ReplyDelete
  47. dear boss boss.humeri company kam krti hay.lohe k main gate or jo mechanical fabrication and other work.

    ReplyDelete
  48. Assalamo Alaikum
    Could you please give your expert opinion on the following? The contractor gave me estimate of Rs, 600, 000. It is a shop in Faisalabad city. He says that his estimated profit is about Rs. 40,000. Time limit 90 day to 120 days.
    1. Plot of shop size: 10 X 20 = 200 feet
    2. Basement roof at 10.5 Feet + Stairs and sliding door + Plaster only
    3. Basement walls 9 inches all sides with pillars + chips outside of walls
    4. Ground floor shop + side walls 9 inches + back wall - shared
    4. Shatter gate + shop front shed + new electricity connection
    5. Iron bars used 3.5 inches Karachi
    6. Top of shop is simple floor of ordinary tiles + drain pipes

    ReplyDelete
    Replies
    1. Salaam dear Muhammad Amjad,
      I am sorry to disappoint you that I am not a professional builder so not able provide you such a technical information.
      Sorry!

      Delete
  49. We provide unique type of Home Building Services in and around Lahore.
    We are building Villas/Houses on Turn Key Basis in various popular locations in and around Lahore. We have not built homes only but credibility and standards too. We have an excellent record of Client satisfaction as successfully delivered so many Villas in Lahore to overseas Pakistanis and Local customers too. Better visit us in person and let us help you build your dream house without any hassle. We have made construction lot easier for our Clients. Please come and visit our sites with us to examine workmanship or other standards whatever.
    CONTACTS:
    Mr. Naeem Wajid
    Mobile: +92 300 9682697
    Mobile: +92 333 6361023

    ReplyDelete
  50. Hi, We are making One Model House In state life Phase 1 interested team for Plaster and Bath and Floor tiles if you are interested please reply by email jdinteriordesign@gmail.com - or call +971 55 6873050 Dubai . Thanks JD

    ReplyDelete
  51. very good information....

    ReplyDelete
  52. Sharoze Ahmed1:51 am

    I have done the construction of two 5 Marla & one 3 Marla double story just started the fourth 10 Marla.

    What I found is to build a good looking house calculate your cost in this way.

    Single story 5 Marla
    (include every thing (labour material tiles kitchen bath room etc)

    Per Marla cost (Rs 450000/- to Rs 470000/-) Total Approx Rs 2250000/- to Rs 2350000/- Approx

    Double Story 5 Marla
    (include every thing (labour material tiles kitchen bath room etc)


    Per Marla Cost (Rs 400000/- to 420000/-) Rs 4000000/- to Rs 4200000/-
    Not more the that at any cost :-)

    Single Story 3 Marla
    (include every thing (labour material tiles kitchen bath room etc)


    Per Marla Cost (Rs 430000/- to 450000/-) Total Rs 1290000/- to Rs 1350000/-
    Not more the that at any cost :-)

    Double Story 3 Marla
    (include every thing (labour material tiles kitchen bath room etc)


    Per Marla Cost (Rs 400000/- to 420000/-) Total Rs 2400000/- to Rs 2520000/-
    Not more the that at any cost :-)

    If you need me to send the complte breakup email me at khanmahroz@hotmail.com or SMS me at 03312602774.

    Thanks

    Sharoze

    ReplyDelete
  53. Anonymous10:07 pm

    Please tell me how Many tons of steel do I need for.7marla house roof only and cement packets please and bricks also please

    ReplyDelete
  54. Hello every one. i build up a house in islamabad area. 5 years back. it cost me Rs=1100/sqft. for grey structure. now the labour rate for grey structure is between 200 ---250per sqft. and the current rate in islamabd; and complete grey structure is Rs-1350/sf. but if u take pain to provide material to contractors. it will cost u 1500 2000 per sq ft. labour rate varies around 250/sf